CONSTRUCTION UPDATES

July 2025 Update:

Work on the high school and elementary school is ongoing. Check out the progress below:

High School:

  • Abatement is complete

  • Restroom underground plumbing installations are complete

  • Existing ceiling demolition is in progress

  • Overhead mechanical, electrical, and plumbing installations are in progress

  • Gym existing block wall demolition is scheduled to begin soon

IMG_5996.jpg
IMG_5997.jpg

Elementary School:

  • Existing window removal is complete

  • Restroom interior framing is complete

  • Plumbing in-wall installations are in progress

  • Overhead mechanical, electrical, and plumbing installations are in progress

4548939A-E8F5-4FCF-93B9-69922E1145B6.jpe
IMG_5964.jpg
B45CB3B1-4301-46A9-9FB3-5CFFAC1F57D6.jpe

April 2025 Update:

Demolition of the gymnasium has begun! Check out the progress below:

IMG_7151.JPG
IMG_5260.jpg
IMG_5255.jpg
IMG_5253.jpg
IMG_5252.jpg