CONSTRUCTION UPDATES
September 2025 Update:
Work on the high school and elementary school is ongoing. Check out the progress below:

High School and Elementary School Renovations:
-
New truss installations are complete
-
Locker room plumbing line installation is in progress.
-
Concrete masonry unit wall work is in progress.
-
Existing flue demolition is in progress.


July 2025 Update:
Work on the high school and elementary school is ongoing. Check out the progress below:
High School:
-
Abatement is complete
-
Restroom underground plumbing installations are complete
-
Existing ceiling demolition is in progress
-
Overhead mechanical, electrical, and plumbing installations are in progress
-
Gym existing block wall demolition is scheduled to begin soon


Elementary School:
-
Existing window removal is complete
-
Restroom interior framing is complete
-
Plumbing in-wall installations are in progress
-
Overhead mechanical, electrical, and plumbing installations are in progress



April 2025 Update:
Demolition of the gymnasium has begun! Check out the progress below: